摘要
针对35 kV变电站升压增容改造工作中供电持续性与施工安全的冲突问题给出成体系的过渡施工办法,参照工程实际操作情况并通过对用电负荷特点的透彻剖析,制订出分步骤倒闸操作与搭配临时过渡接线的执行策略,着重研究电气主接线调整方式、设备更换操作流程及现场安全风险管理手段,并纳入环境影响控制办法。实际应用成效显示,该方案成功化解施工期间供电难题、保障电网安全平稳运行且为类似老旧变电站改造工程提供可参考的实际案例。
Transition Scheme During the Voltage Upgrade and Capacity Expansion Construction of a 35kV Substation
Ying Yang
Author Information
- Guangxi Zhengyuan Supervision Consulting Co., Ltd., Nanning 530000, Guangxi Province, China
Abstract
Addressing the conflict between power supply continuity and construction safety during the voltage upgrade and capacity expansion of a 35 kV substation, a systematic transition construction method is proposed. Based on actual project operation and a thorough analysis of load characteristics, an execution strategy involving step-by-step switching operations and temporary transition wiring is formulated. The study focuses on the adjustment methods for the main electrical wiring,equipment replacement procedures, and on-site safety risk management measures, while also incorporating environmental control considerations. Practical application results demonstrate that this scheme successfully resolves power supply challenges during construction, ensures the safe and stable operation of the power grid, and provides a practical reference case for similar renovation projects of aging substations.